top of page

Our Quality Policy

Bryant Machine is dedicated to delivering exceptional quality parts on time, with a strong commitment to customer satisfaction. We achieve this through continuous improvement and strict adherence to the AS9100 quality management system. 

ISO 9001 & AS9100

To ensure consistent delivery of the highest quality and the on-time delivery customers expect, we are currently pursuing ISO 9001 and AS9100 certification. This demonstrates our commitment to meeting the strict standards required by these internationally recognized quality management systems.

Supplier P.O. Clause

1. Customer Right of Inspection

Bryant Machine and their customer and regulatory authorities has the right of access by the organization to the applicable areas of all facilities, at any level of the supply chain involved in the order and to all applicable records. 

2. Certification / Prevention of Counterfeit Parts

Supplier shall sign and certify that all parts, material and processes were inspected and found to comply with the requirements of this order. The revision level that processes were completed must be listed on any documentation. (Suspect) Counterfeit Parts are not allowed. 

3. Processes / Part Revision

All processes, parts, drawings, specifications, etc. listed on this purchase order shall be done per latest revision unless stated otherwise per the purchase order.

4. Traceability

Traceability must be maintained for all work done on this purchase order. This includes lot, batch, and heat #s of material used for processes and the revision level of the process used for this PO. Material certs are required for materials used in fabrication.

5. Records Retention

Any records made while processing this purchase order not sent to Bryant Machine must be kept safe and accessible. Records shall be kept a minimum of 10 years unless otherwise stated, and they destroyed via deletion or shredding.

6. Authorized Markings

Only markings listed on the drawing and parts list are allowed directly on parts, including acceptance and date stamps. 

7. Change in Process

Supplier must notify Bryant Machine of changes in product and/or process, changes of suppliers, manufacturing facility location, and, where required, obtain Bryant Machine approval.

8. Verification & Bryant Machinedation (Test) Acceptance

Supplier, where appropriate agrees to requirements for design, test, inspection, verification, use of statitstical techniques for product acceptance, and related instructions for acceptance on PO, and as applicable critical key items/key characteristics. 

9. Test Specimens

Supplier, where appropriate, agrees to PO requirements for test specimens for design approval inspection/verification, investigation or auditing. 

10. Shelf Life

Data shall be provided for item or materials which are susceptible to degradation with age. Supplier shall provide a signed statement with shelf life, starting date, and expiration date and storage requirements. Shelf-life limited items shall have 75% or more of their shelf life remaining at time of the delivery to Bryant Machine. 

11. Identification

At a minimum, all items including raw material supplied on the Bryant Machine PO will be identified on supplier's paperwork with the part name and #, as specified on the PO. The identification and revision status of specifications, drawings, process requirements, inspection/verification instructions and other relevant technical data must be included.

12. Shipping

Materials shall be packaged, handled and transported in a way to ensure the quality of material/part, and that damage, deterioration and loss in transit are prevented. 

13. Corrective Action

Supplier shall, upon request, provide statements of corrective action on nonconforming material/parts. Corrective action may require approval signatures by Bryant Machine and customer/regulatory representatives. 

14. Material Substitutions Prohibited

Unauthorized material substitutions are not permitted. This includes any deviation of form, size, shape, chemistry, melt method, origin, temper/condition, product testing or surface finish. Conversion of raw material (i.e., heat treat to change temper or condition) constitutes material substitution. Raw material must not be re-certified with respect to thickness, diameter, and width or cross-sectional area or product form. Certification for material shall reflect the form and size originally manufactured. 

15. National Defense Rated Orders

If orders are Rated/certified for national defense, emergency preparedness and/or energy programs, the supplier shall follow all the requirements of the defense priorities and allocation system regulation (15CFR700).

16. Flow-down Requirements

The supplier must flow down the supply chain the applicable requirements including customer requirements. 

17. Nonconforming Product

Supplier must notify Bryant Machine of nonconforming product and obtain Bryant Machine approval for nonconforming product disposition. 

18. QMS Requirements

Supplier shall implement and maintain a Quality Management System, preferably compliant to at least ISO 9001, unless otherwise called out on the Purchase Order. 

19. Designated Approved Eternal Providers

When required, only customer-designated or approved suppliers will be used. 

20. Awareness for Employees

Supplier ensures employees are aware of their contribution toward: (a) Product/Service Conformity, (b) Product Safety, and (c) importance of ethical behavior

bottom of page